Optimization Process¶
Optimization proceeds in three phases: removing tasks, replacing tasks, and finally generating a subgraph containing only the remaining tasks.
Assume the following task graph as context for these examples:
TC1 <--\ ,- UP1
, B1 <--- T1a
I1 <-| `- T1b
` B2 <--- T2a
TC2 <--/ |- T2b
`- UP2
Removing Tasks¶
This phase begins with tasks on which nothing depends and follows the dependency graph backward from there – right to left in the diagram above. If a task is not removed, then nothing it depends on will be removed either. Thus if T1a and T1b are both removed, B1 may be removed as well. But if T2b is not removed, then B2 may not be removed either.
For each task with no remaining dependencies, the decision whether to remove is
made by calling the optimization strategy’s should_remove_task
method. If
this method returns True, the task is removed.
The optimization process takes a do_not_optimize
argument containing a list
of tasks that cannot be removed under any circumstances. This is used to
“force” running specific tasks.
Replacing Tasks¶
This phase begins with tasks having no dependencies and follows the reversed dependency graph from there – left to right in the diagram above. If a task is not replaced, then anything depending on that task cannot be replaced. Replacement is generally done on the basis of some hash of the inputs to the task. In the diagram above, if both TC1 and I1 are replaced with existing tasks, then B1 is a candidate for replacement. But if TC2 has no replacement, then replacement of B2 will not be considered.
It is possible to replace a task with nothing. This is similar to optimzing away, but is useful for utility tasks like UP1. If such a task is considered for replacement, then all of its dependencies (here, B1) have already been replaced and there is no utility in running the task and no need for a replacement task. It is an error for a task on which others depend to be replaced with nothing.
The do_not_optimize
set applies to task replacement, as does an additional
existing_tasks
dictionary which allows the caller to supply as set of
known, pre-existing tasks. This is used for action tasks, for example, where it
contains the entire task-graph generated by the original decision task.
Subgraph Generation¶
The first two phases annotate each task in the existing taskgraph with their fate: removed, replaced, or retained. The tasks that are replaced also have a replacement taskId.
The last phase constructs a subgraph containing the retained tasks, and simultaneously rewrites all dependencies to refer to taskIds instead of labels. To do so, it assigns a taskId to each retained task and uses the replacement taskId for all replaced tasks.
The soft-dependencies are then solved for each task, by adding all the remaining tasks in the subgraph from that list to its dependencies.
The result is an optimized taskgraph with tasks named by taskId instead of
label. At this phase, the edges in the task graph diverge from the
task.dependencies
attributes, as the latter may contain dependencies
outside of the taskgraph (for replacement tasks).
As a side-effect, this phase also expands all {"task-reference": ".."}
and
{"artifact-reference": ".."}
objects within the task definitions.